A new crisis has escalated in Libya's oil sector after armed men closed a valve on the crude transport line from the Sharara field, the country's largest oil field, to Zawiya, causing a loss of about 130,000 barrels of daily production. At the same time, protesters closed the gates of the Zawiya refinery and prevented workers and technicians from entering it.
The National Oil Corporation warned that continued disruption could halt production, transport and exports from the Sharara field, forcing it to declare "force majeure", at a time when oil is the main source of revenue for the Libyan state.
The crisis began on the morning of Monday, 21 September 2026 (10 Rabi al-Akhir 1448 AH), when an armed group closed valve No. 7 on the pipeline carrying crude from the Sharara field to the port of Zawiya in western Libya.
The corporation said the closure caused pressure to rise within the crude transport line, leading to a significant drop in the field's output.
In a later update on Tuesday, the corporation said production losses resulting from the closure of the Sharara–Zawiya line had reached about 130,000 barrels per day.
Libya's largest oil field
The Sharara field, located in south-western Libya, is the largest oil field in the country, with a production capacity of about 340,000 barrels per day, making it a key element of Libyan crude output.
The field is operated by Akakus Oil Operations, while the crude is transported through a long pipeline to Zawiya on the western coast, where the refinery and export facilities are located.
The National Oil Corporation said it had contacted the South-West Oil Facilities Guard branch and asked it to intervene, but these contacts did not initially lead to the valve being reopened.
It added that technical teams had been unable to reach the area surrounding valves No. 6 and No. 7.
In its first statement, the corporation did not disclose the identity of the armed group that closed the valve.
Facilities guards and an armed group
However, a new statement from the National Oil Corporation, issued on 22 September 2026 (11 Rabi al-Akhir 1448 AH), provided further details on the crisis, saying that the continued closure of valve No. 7 in the al-Hamada area is being maintained by elements of the South-West Oil Facilities Guard alongside an armed group.
This comes amid protests by members of the Oil Facilities Guard which, according to local and international reports, are linked to demands concerning wages and employment conditions.
The corporation did not clarify whether the armed group it referred to in its first statement was entirely separate from the protesting Facilities Guard elements, so the identity of all those involved in closing the line remains unclear.
Closure of Zawiya refinery gates
The crisis is no longer limited to the Sharara pipeline.
The National Oil Corporation announced that a group of Oil Facilities Guard members had also closed the gates of the Zawiya Oil Refining Company and the Brega Oil Marketing Company.
The corporation said the closure prevented employees and technicians from entering the facilities and disrupted the night-shift rotation necessary for continued operation, and also prevented students of the Zawiya Oil Institute from reaching their studies.
The Brega gate was partially reopened later, but the main gate of the Zawiya refinery remained closed, according to the corporation's latest statement.
The corporation warned that current conditions do not allow operations to resume normally and safely inside the refinery.
Warning of a halt to Sharara and exports
The National Oil Corporation warned that continued closure of the valve would ultimately lead to a halt in production at the Sharara field, along with a halt in the transport and export of crude.
It said this would reduce state revenues and expose the oil transport network and its facilities to technical and operational risks.
It also warned that continued disruption could bring the Zawiya refinery to a standstill, which would force Libya to increase its imports of refined fuel from abroad and raise costs to the state.
The corporation threatened to declare "force majeure" if the closure continued, a legal measure that allows contractual obligations to be suspended when circumstances beyond control prevent their fulfilment.
Not the first crisis this September
The Sharara crisis follows only days after another disruption affecting Libya's oil infrastructure.
On 15 September 2026 (4 Rabi al-Akhir 1448 AH), the National Oil Corporation announced that members of the Oil Facilities Guard had closed, without authorisation, the main export line "al-Hamada–Zawiya".
According to the corporation, the closure led to a sudden rise in pressure and a complete halt of operations at the al-Hamada field, the al-Tahara field and the NC5 station.
The corporation also spoke at the time of threats to close the north al-Hamada field and other fields and wells, and rejected the use of oil facilities as a means of pressure to achieve protest demands.
Oil once again as a bargaining chip
Recent developments bring back into focus the fragility of Libya's oil sector in the face of security and political disputes and local protests.
Since the fall of Muammar Gaddafi's regime in 2011, oil fields, pipelines and ports have repeatedly been shut down by armed groups, local forces and protesters seeking political or economic demands.
The current crisis gains additional significance because of the size of the Sharara field; the field alone accounts for a large part of Libya's production capacity, and any complete and prolonged halt would have a direct impact on the country's output, exports and revenues.
Libya's disruptions also come at a time when global energy markets are experiencing sharp fluctuations against the backdrop of tensions and wars in the region, which makes markets more sensitive to any additional loss of supply.
Between the closure of the Sharara line and the disruption of work at the Zawiya refinery, the National Oil Corporation now faces a crisis extending across the production, transport and refining chain, and its development remains tied to reopening the valve and facilities and securing access for technical teams to reach them.